Sunday, May 9, 2010

The Fifth Week


3th May 2010,

- install tubing for Leak Tester machine.
* violet tube with the size of 4 mm used.
* Y fitting used for the tube.
* cable tight used to tidy up the tube.
- assemble Seal machine component part.
- printing and labeling the tube for Leak machine.
* green function as extending the air and yellow function as retracting the air.
- assemble sensors on cylinder for Seal machine.


4th May 2010,

- install Seal machine component part.
* Seal is a machine that seal the hardisk from leaking.
- assemble utility component assembly for every machine.
* install fitting for utility component assembly.
* the fitting is L fitting with the size of 4mm, 8mm and 12mm.
- install dowel pin on stand plate for Seal machine.


5th May 2010,

- assemble machine component part for every machine.
* used mechanical diagram as reference to assemble the part.
- wiring the light for every machine.
* used four core wire to connect the light with input output terminal block.
* red, yellow, green and black colours of the wire must be connect correctly.
- prepare din rail for LN2 project machines.
- install sensors on cylinder for another Seal machine.


6th May 2010,

- help engineer arrange component that have just arrived.
- dumped the trash at the garbage place.
- rewire the wiring for End Effector.
* End Effectors used for TVCM, Latch, ARIRI, Spacer and Plug machines.
* it is used with the robot to install specified component according to the machine.
- moved base structure for LN2 project to assembly place.


7th May 2010,

- wiring component plate for APCBA machine.
- install relay on APCBA component plate.
- install RAM on APCBA CPU's.
- change new motherboard for APCBA CPU's.
- tidy up wiring for APCBA.
* used cable tight to tie wire together nicely.