Monday, June 21, 2010

The NInth Week


31th May 2010,

- assemble component part for datum ARIRI.
* assemble prism glass.
* reassemble sensors for cylinder.
* align the prism glass.
* align spotlight to be correctly placed so it can point the ramp.
* assemble ring light on datum.
* assemble light box.
- assemble datum on conveyor.
- adjust the alignment of the conveyor.


1th June 2010,

- wiring ARIRI's datum.
* wiring the light box.
* light box is the power supply for laser.
* wiring fiber optic to terminal block.
* used molex clamper to clamp molex with wire.
* used two core wire to connect the fiber optic and the ring light.
* insert the molex to molex head.
* molex head has two type that is male and female.
* connected the head and the wire will be connected.


2nd June 2010,

- assemble the part lift on conveyor.
* lift the conveyor to install the part lift.
* align the part lift so it is properly placed.
* tidy up the wire so the part lift can fit in without damaging the wire.
* screwed the part lift.
* screw must be screwed to the nut that already placed on the conveyor.


3rd June 2010,

- do tubing for ARIRI,
* some tube are misplaced and need to be corrected.
* the tube are connected to part lift ,cylinder and crowder bias.
* then it is connected to device net.
* for ARIRI there is two part lift that is at zone 2 and zone 5.
* the tube is yellow and green for retract and extend.


4th June 2010,

- tidy up ARIRI.
* placed the wire nicely and put cable tight.
- wiring the sensors from the cylinder.
- the cylinder at pogo block and laser detector.
- connect the laser controller cable.